COMMISSIONING AND TESTING 调试和试验
(a)
The commissioning shall be carried out in accordance to the
procedures set out in Schedule 5. 调试应按照在附录5中阐明的规程进行。
(b)
The Company shall provide to EDC within fifteen (15) Days after the
Commercial Operation Date or date of Provisional Operation, as
applicable, copies of all test results of the relevant
Commissioning Test(s).
公司应在商业运行日或临时运行日之后的十五(15)天内,向柬埔寨电力公司(EDC)提交一份相关调试试验的所有试验结果副本。
(c)
EDC shall accept all test energy from the Project and will dispatch
a Unit upon the request of the Company so as to allow for timely
completion of all tests by the Company at any
time.
EDC应接受项目的所有试验电量并根据公司要求调度机组以便公司能够按时完成所有试验。
4.5
CONSTRUCTION AND O&M CONTRACTORS 施工和运行&维护承包商
(a)
The appointment or any change of the Construction Contractor shall
not relieve the Company of any of its obligations under this
Agreement. The Company shall not replace the Construction
Contractor without the prior written consent of EDC, which consent
shall not be unreasonably withheld or delayed where:
指定或更换施工承包商不得免除公司在本协议项下的任何义务。未经EDC的事先书面同意,公司不得更换施工承包商,如满足下列条件则EDC不得无理拒绝或拖延同意。
(i)
the Company has provided EDC with the evidence referred to in
Section 4.2 (a)(ii) in relation to the proposed new Construction
Contractor; and
公司已根据第4.2(a)(ii)条要求向EDC提交关于拟议新施工承包商的证据;
(ii)
the terms of the proposed new Construction Contract are in
accordance with the Specifications and the terms of this
Agreement.
拟议的新施工合同条款符合规范和本协议条款规定。
The Company shall not, without the prior
written consent of EDC, waive any of its rights under or make any
amendment to the Construction Contract which:
未经EDC的事先书面同意,公司不得放弃其在施工合同项下的任何权利,或对施工合同作出下列修改:
(A) materially
relieves the Construction Contractor of or materially reduces its
obligations thereunder or reduces the amount of any security
provided to the Company thereunder;
and
实质性解除或减少施工承包商在施工合同项下的义务或减少提供给公司的担保的金额;
(B) materially and
adversely affects the rights and/or obligations of EDC under this
Agreement or would result in any increase in the amount which EDC
is required to pay under this Agreement.
严重影响EDC在本协议项下的权利和/或义务,或导致EDC根据本协议应付款项的增加。
(b)
The appointment of the O&M Contractor shall not relieve the
Company of any of its obligations under this Agreement. The Company
shall not replace the O&M Contractor without the prior written
consent of EDC, which consent shall not be unreasonably withheld or
delayed where (i) the Company has provided EDC with the evidence
referred to in Section 4.2 (b)(ii) in relation to the proposed new
O&M Contractor; and (ii) the terms of the proposed new O&M
Agreement are consistent with Prudent Utility Practices, the
Operations and Maintenance Plan and the terms of this
Agreement.
指定运行&维护承包商不应解除公司在本协议项下的任何义务。未经EDC的事先书面同意,公司不得更换运行&维护承包商,如满足下列条件则EDC不得无理拒绝或拖延同意::(i)公司已根据第4.2(b)(ii)条要求向EDC提供关于拟议新运行&维护承包商的证据(ii)拟议的新运行&维护协议条款符合审慎应用惯例、运行维护计划和本协议条款规定。
The Company shall not, without the prior
written consent of EDC, waive any of its rights under or make any
amendment to the O&M Agreement which:
经EDC的事先书面同意,公司不得放弃其在运行&维护协议项下的任何权利,或对运行&维护协议作出下列修改:
(i)
relieves the O&M Contractor of or materially reduces its
obligations thereunder or reduces the amount of any security
provided to the Company thereunder; and
解除或减少运行&维护承包商在运行&维护合同项下的义务或减少提供给公司的担保的金额;
(ii) materially and adversely affects
the rights and/or obligations of EDC under this Agreement or would
result in any increase in the amount which EDC is required to pay
under this Agreement. 严重影响EDC在本协议项下的权利和/或义务,或导致EDC根据本协议应付款项的增加。
4.6
OPERATING PROCEDURES 运行大纲
(a)
No later than sixty (60) days prior to the date of Provisional
Operation of the First Unit, the Company and EDC shall jointly
develop operating procedures addressing operational interfaces
between EDC and the Company, including the method of day-to-day
communications, notification of key personnel lists, clearances and
switching practices, outage scheduling, capacity and energy
reporting, operations logging, procedures in relation to Dispatch
of the Project and Reactive Power conditions (the “Operating
Procedures”).
不晚于首台机组临时运行日前60天,公司和EDC应共同准备运行大纲,选择EDC和公司之间的运行接口,包括日常通讯的方法、通知主要人员名单、消缺和开关测试、停机计划、容量和电能报告、操作记录、关于项目调度程序和无功功率的条件(“运行大纲”)。
(b)
The Operating Procedures shall take into proper account and be
consistent with (i) the design of the Project and the
Interconnection Facilities; (ii) the EDC Grid Code; (iii) the draft
of written operating procedures provided by the Company pursuant to
Section 4.2(f); and (iv) the Technical Limits.
运行大纲应考虑并符合:(i)项目设计和互联设备;(ii) EDC电网规范;(iii)由公司依照第4.2(f)条提交的书面运行大纲草稿;及(iv) 技术限制。
4.7
OBSERVATION BY EDC EDC的检查
EDC and its representative shall have
the right at any time during normal business hours, upon reasonable
prior notice to the Company, to observe the progress of the
construction and start-up of the Project and its Testing and
Commissioning.
经事先合理通知公司,EDC及其代表有权在正常工作时间检查项目施工进度、启动、试验和调试。
4.8
ENERGY DURING TESTS 试验期间的供电量
Prior to the Commercial Operation Date
of the Project and/or the date of Provisional Operation of a Unit,
EDC shall accept all energy produced by a Unit during the
Commissioning Tests and shall pay for such energy in accordance
with Section 8.3(a). After the Commercial
Operation Date of this Phase or date of Provisional Operation of a
Unit, EDC shall accept energy produced during any test and such
energy shall constitute Net Electrical Output for purposes of this
Agreement. 在项目商业运行日期和/或机组临时运行日期之前,EDC应接收机组调试试验期间产生的所有电量并应根据第8.3(a)条付款。在本期商业运行日期或机组临时运行日期后,EDC应接收任何试验期间产生的电量并且该电量构成本协议项下的净电输出。
4.9
STANDBY POWER备用电源
Following the Energization Date, EDC
shall use reasonable efforts to make available to the Company
standby electrical power at rates for large industrial customers
upon the request of the Company. In lieu of using standby
electrical power, the Company may utilize self-generated power
(which shall not be metered at the Metering Point) to provide for
Commissioning or other power needs at its own cost.
在通电日之后,EDC将努力根据公司的要求提供大型工业客户级备用电源。公司可以自费使用自发电(不会在计量点计量)用于调试或其他电力需求替代备用电源。
5.
CONTROL AND OPERATION OF THE PROJECT项目控制和运行
5.1
OPERATIONAL REQUIREMENTS 运行要求
(a)
The Project shall be operated as a base load generating plant
dispatched for Base Load Operation and generating at a level of
output consistent with the design parameters and reasonably
efficient operation, except during periods of downtime and outages,
and in accordance with the Commercial Operations
Programme.
本项目为基本负荷发电厂,根据基本负荷运行调度,并根据设计参数和合理高效运行要求的输出水平发电,除非根据商业运行计划停机。
(b)
The Company shall operate and maintain the Project in accordance
with this Agreement, including the Specifications, the Operating
Procedures, Prudent Utility Practices, and all applicable Law and
in so doing shall establish environmental management systems and
facilities and occupational health and safety procedures to ensure
that all applicable Law are complied with or exceed.
公司应按照本协议包括规范、运行大纲、谨慎应用惯例和所有适用的法律运行和维护项目,并应建立环境管理体系和设施以及职业健康和安全程序,以确保高标准符合所有适用的法律。
(c)
Subject only to the Technical Limits, the Company shall at all
times keep, operate and maintain the Project consistent with
Prudent Utility Practices and in such a manner as not to have a
adverse effect on the operation of the EDC System.
遵守技术限制,公司保持、运行和维护项目应始终遵守审慎应用惯例,并不得对EDC系统的运行造成不良影响。
(d)
The Company shall install protective relays within the Project and
the Interconnection Facilities in accordance with the
Specifications, having ratings and characteristics previously
approved in writing by EDC (such approval not to be unreasonably
withheld or delayed) and shall maintain the settings of all such
relays at levels acceptable to EDC within the Technical Limits. The
Company shall not change the settings of such relays without the
prior written consent of EDC, which consent shall not be
unreasonably withheld or delayed.
公司应按照规范在项目和互联设施内安装保护继电器,该继电器的等级和特性应由EDC事先书面批准(该批准不得被无理拒绝或拖延),公司应在技术限制内保持EDC可接受水平的继电器组件。未经EDC事先书面同意,公司不得更改此类继电器组件,该同意不得被无理拒绝或拖延。
(e)
The Company shall operate the Project in parallel with the EDC
System and in accordance with EDC’s technical requirements, the
Specifications and all applicable Law including guidelines relating
to synchronization, voltage control and generation of harmonic
frequencies furnished to the Company.
公司运行项目应与EDC系统并联,并应遵守EDC的技术要求、规范和所有适用的法律,包括提供给公司的关于同步、电压控制和产生谐波频率的指南。
5.2
DISPATCH BY EDC EDC的调度
Subject to Section 2.5, EDC shall have
the right to dispatch each Unit during Provisional Operation and
after the Commercial Operation Date of this Phase in accordance
with Economic Dispatch provided that the Dispatch Instructions are
consistent with the Technical Limits, the Commercial Operations
Programme, the Operating Procedures and the planned Minimum Output.
If a particular Dispatch Instruction would force the Project to
operate outside the Technical Limits, the Company must promptly
notify EDC of this fact in accordance with the procedures set out
in the Operating Procedures and shall not respond to any Dispatch
Instruction which violates the Technical Limits.
根据第2.5条,EDC有权在临时运行时并在本期商业运行日之后根据经济调度来调度每台机组,前提是调度指令应符合技术限制、商业运行计划、运行大纲和计划最小输出。如果某一调度指令要求项目超出技术限制运行,公司应根据运行大纲中规定的程序立即通知EDC并且不得响应违反技术限度的调度指令。
5.3
OPERATION BY THE COMPANY 公司进行的运行
(a)
Subject to Section 5.2, the Company shall control and operate each
Unit after it enters Provisional Operation and the Project after
the Commercial Operation Date in accordance with Dispatch
Instructions.
根据第5.2条,公司应按照调度指令,在进入临时运行后控制和运行每台机组,并在商业运行日期后控制和运行项目。
(b)
Commencing with the Provisional Operation of the First Unit, the
Company shall inform the Control Center of the availability of all
Units then in Provisional Operation or after the Commercial
Operation Date of each phase, in Commercial Operation, and will
promptly advise the Control Center of any changes in the
availability of a Unit or the Project in accordance with the
Operating Procedures.
在第一台机组开始临时运行时,公司应通知控制中心所有机组在临时运行或在各期商业运行时的可用性,并应按照运行大纲及时通知控制中心关于机组或项目可用性的任何变化。
5.4
PLANNED AND OTHER OUTAGES 计划停机和临时停机
(a)
At least sixty (60) Days prior to each date of Provisional
Operation of a Unit and the Commercial Operation Date of each
phase, the Company shall submit to EDC its desired schedule of
Planned Outage periods for the period for each relevant Unit from
its date of Provisional Operation and the Commercial Operation
Date, as applicable, to the end of the following calendar year. By
July 1 of the said following calendar year and each calendar year
thereafter, the Company shall submit to EDC its desired schedule of
Planned Outage periods for the following calendar year. The Company
may schedule up to the number of days of Planned Outages for each
calendar year, which are specified in the Operations and
Maintenance Plan. The Company shall: (i) not schedule more than one
(1) Unit for a Planned Outage (ii) not schedule during the period
from January through June and shall use reasonable efforts to
prevent a complete Outage of another Unit while a Unit is
undergoing a Planned Outage and if any such Outage occurs to return
the affected Unit to service as soon as possible consistent with
Prudent Utility Practices.
至少在首台机组的临时运行和每期商业运行日期前60天,该公司应向EDC提交该机组从临时运行日期和商业运行日期(如适用)到下一个日历年年底的计划停机预期计划。在下一个日历年及其后每一个日历年的7月1号,公司应向EDC提交下一日历年的计划停机预期计划。公司可安排每一日历年的计划停机天数并规定在运行维护计划中。公司(i)不得安排超过一台机组的计划停机(ii)不得在1月至6月期间安排计划停机,并且应尽力防止一台机组在另一台机组计划停机时完全停机,如果这样的情况发生则应根据谨慎应用惯例尽快恢复该机组。
(b)
At least fourteen (14) days prior to each date of Provisional
Operation of a Unit and the Commercial Operation Date and two (2)
months prior to the commencement of each calendar year, as
applicable, EDC shall acting reasonably notify the Company in
writing whether the requested Planned Outage periods are
acceptable. If EDC does not accept any of the requested Planned
Outage periods, EDC shall advise the Company of a period when EDC
determines such unacceptable Planned Outage period can be
rescheduled. Such rescheduled periods shall be as close as
reasonably practicable to the requested periods and shall comply
with the Technical Limits. The Company’s conduct of Planned Outages
shall be subject always to Sections 5.4 (d) and 5.6 (b).
至少在每个机组临时运行日期和商业运行日期前 14天以及每个日历年开始前2 个月,如适用, EDC应书面通知公司确认要求的计划停电期限是否可接受。如EDC不接受,EDC应向公司建议一个调整的计划停机期限。该重新调整的期限应尽量接近公司要求的期限并应符合技术限制。公司执行计划停机应始终遵守第5.4(c)和5.6 (b)条。
(c)
Commencing with the Commercial Operation Date of each phase, or the
date of Provisional Operation of the First Unit, the Company may
schedule the number of days of Planned Outages for each Operating
Year after the Commercial Operation Date or month during
Provisional Operation as stated in the Operations and Maintenance
Plan.
自各期商业运行日期或第一台机组的临时运行日起,公司应按运行和维护计划安排商业运行日期后每个运营年或临时运行期间的计划停机天数。
(d)
EDC may, upon giving at least sixty (60) days prior written notice,
require the Company to reschedule a Planned Outage, provided,
however, that the Company shall not be obligated to change the
schedule of such Planned Outage in a manner or at a time outside
the Technical Limits or contrary to Prudent Utility
Practices. EDC shall compensate the Company for
the additional incremental costs incurred as a result of
rescheduling a Planned Outage, including mobilization costs payable
to the Company’s contractors, resulting from any rescheduling by
EDC under this Section 5.4(d).
EDC可提前60天发出书面通知要求公司重新安排计划停机,但是公司无义务按超出技术限制或违反审慎应用惯例的方式或时间改变计划停机计划。EDC应补偿重新安排计划停机而导致的额外费用,包括付给承包商的动员费。
(e)
EDC shall use its reasonable efforts to coordinate its maintenance
program for the Interconnection Facilities with Planned Outages so
as to minimize any disruption to the operation of the
Project.
EDC应努力协调互联设备的维护计划和计划停机,尽量避免中断项目运行。
(f)
When in the opinion of the Company the circumstances warrant a full
or partial short term maintenance outage (a “Short Term Maintenance
Outage”), the Company shall give to EDC not less than two (2) Days’
prior written notice specifying the circumstances in reasonable
detail and the date and time of commencement and estimated duration
of the proposed Short Term Maintenance Outage. EDC may, in its sole
discretion which shall be exercised taking into account the
Technical Limits and so as not to damage the Project, approve the
proposed Short Term Maintenance Outage and if it does not do so, it
shall grant the Company the right to schedule and conduct such
Short Term Maintenance Outage at a time acceptable to EDC within a
reasonable period from the time of the request. The Company shall
conduct Short Term Maintenance Outages subject always to Section
5.6(b).
如果公司认为有情况需要全部或部分短期维护停机(“短期维护停机”),公司应至少提前2天书面通知EDC说明该情况的合理细节以及建议短期维护停机的开始时间和预计期限。EDC应考虑技术限制,在不影响项目的前提下,批准此短期维护停机计划。如果EDC不同意该计划,EDC应授权公司在EDC可接受的期限内安排和进行该短期维护停机。公司应始终依据第5.6(b)条进行短期维护停机。
(g)
The Company shall notify EDC’s Control Centre as soon as is
practical regarding the occurrence of any Forced Outage affecting a
Unit, the steps being taken to rectify the cause of the Forced
Outage and the expected duration of the Forced
Outage. When, following a Forced Outage, a Unit
is ready to return to full service, the Company will notify the EDC
Control Centre and at the time of such notice the Company will also
notify the EDC Centre of the Dependable Capacity of the
Unit.
公司应在发生影响机组的强制停机时立即通知EDC控制中心、并说明为修复导致强制停机的情况所采取的步骤以及强制停机的预计时间。在强制停机后,当机组能够恢复全面运行时,公司应通知EDC控制中心并同时告知机组的可靠容量。
5.5
OUTAGE ALLOWANCES 停机容许量
(a)
The Company shall be entitled to and shall have a periodic Outage
Allowance during the Term as specified in Schedule 13 of this
Agreement, each such allowance effective as of 12:00 am on the
first Day of the relevant Billing Period or Operating Year for such
period as specified in Schedule 13.
公司有权根据本协议附件13的规定获得周期性的停机容许量,该容许量从相关结算期或运行年的首日12:00am生效,期限按附件13规定。
(b)
Outage Allowances shall be used by the Company to offset reductions
of capacity by Hour during which the Project or any part thereof is
not available for Dispatch due to, and to the extent of, an Outage
or a partial Outage (the latter being a deration of capacity during
an Outage) during any Hour in an Operating Year or month during
Provisional Operation on a kWh by kWh basis.
Outage Allowances shall be depleted as and when used to offset
qualifying Shortfall (SH) (as defined in Schedule 13, Section
1.1(a)).
停机容许量应被用于抵消项目容量小时的减少,其无法调度的原因是任何运行年或临时运行月份的以kWh为基础的停机或部分停机(部分停机指停机期间容量的解除配给)。停机容许量在抵消合格短缺量(SH,在附件13第1.1(a)条中定义)时应相应减少。
(c)
If at the end of any Operating Year or month of Provisional
Operation the Company has not experienced an aggregate number of
Hours of Outages (including partial Outages) to fully deplete the
available Outage Allowance and has thus not used all of the Outage
Allowance for that period just completed, the unused Outage
Allowance for such period shall be added to the Outage Allowance
for the next month of Provisional Operation or first Operating
Year, or, subject to Section 5.5(d), a later Operating
Year. Carry forward Outage Allowances shall then
become part of the Outage Allowance for that and any subsequent
period until fully depleted or they expire in accordance with
Section 5.5(d).
如在任何运行年年末或临时运行月份的月末,公司的停机(包括部分停机)小时总额未能用尽可抵消的停机容许量,因此该期限内的停机容许量未全部使用,则该期限内未使用的停机容许量应被加入下一临时运行月份或首个运行年的停机容许量中,或者根据第5.5(d)条加入下一运行年。从上期结转过来的停机容许量将成为后续期限内的停机容许量,直到全部抵消或根据第5.5(d)条失效。
(d)
Unused Outage Allowances that have not been applied or become
applicable against Shortfall as of 11:59:59 pm on the last day of
an Operating Year shall carry forward as described in Table
5.5(d):
未使用的或未抵消短缺量的停机容许量在每个运行年最后一天的11:59:59pm,应按照表5.5(d)的规定结转:
Any unused Outage Allowance in excess of
the maximum carry forward amounts set forth in Table 5.5(d) shall
expire and be of no further effect. The
recurrence of Allowance Periods and Major Maintenance Years shall
be adjusted as appropriate in order to reflect the actual
maintenance cycles of the Project based on the recommendations of
the original equipment manufacturer and the Technical Limits, as
EDC may consent, such consent not to be unreasonably withheld or
delayed.
超过表5.5(d)规定的最大结转量的未使用停机容许量将失效。容许量期限的循环和主要维护年应基于原设备制造商的建议和技术限制适当调整以反映项目的实际维护周期,上述调整应经EDC同意且EDC不得无理拒绝或拖延同意。
(e)
The Company shall be liable for Shortfall Payments under Schedule
13 in any period only when the Outage Allowance (including any
carry forwards) for such period has been depleted.
当期限内的停机容许量(包括结转量)用完时,公司应支付附件13项下的短缺量付款。
5.6
EMERGENCIES 紧急情况
(a)
EDC and the Company shall jointly establish plans for operating the
Project after the date of Provisional Operation of the First Unit
during an Emergency. Such plans shall include recovery from a local
or widespread electrical blackout and voltage reduction in order to
affect load curtailment.
EDC和公司应共同建立第一台机组临时运行日期后在紧急情况下的运行计划,这些计划应包括从当地或者更大范围的断电恢复和影响负荷削减的降压计划。
(b)
During an Emergency and upon the receipt of Dispatch Instructions,
the Company shall supply such power as requested by EDC within the
Technical Limits. If the Project has a Planned Outage or a Short
Term Maintenance Outage and such Planned Outage or Short Term
Maintenance Outage occurs or would occur coincident with an
Emergency, the Company shall use its best effort to reschedule the
Planned Outage or Short Term Maintenance Outage or, if the Planned
Outage or Short Term Maintenance Outage has begun, to expedite the
completion of the work to restore Electricity supply as soon as
possible. EDC shall compensate the Company for
the additional incremental costs incurred as a result of
rescheduling a Planned Outage, including mobilization costs payable
to the Company’s contractors, due to requests from EDC for
Emergency operation unde
r this Section 5.6(b).
在紧急情况中及在收到调度指令后,公司应在技术限度内向柬埔寨电力公司(EDC)供电。如果该项目计划停机或短期维护停机时,同时发生紧急情况,公司应尽力重新安排计划停机或短期维护停机。如果停机已经开始,应加速完成工作并尽快恢复电力供应。EDC应对重新安排计划停机导致的额外成本增加,向公司做出补偿,其包括在本章5.6(b)条,因EDC要求紧急运行公司承包商产生的动员费用。
5.7
Personnel 工作人员
(a)
The Company shall employ personnel, directly or indirectly, who are
adequately qualified and experienced for operating and maintaining
the Project and for coordinating operations of the Project with the
EDC System. The Company shall ensure that such personnel are on
duty at the Project at all times, twenty-four (24) hours a day and
seven (7) days a week commencing with the Provisional Operation of
the First Unit to ensure the operation of the Project in accordance
with this Agreement.
公司应直接或间接地聘用那些在项目运行和维护及协调EDC系统项目运行方面有足够资格和经验的人员。公司应确保这些人员从第一台机组临时运行开始,一直在项目的工作地点上班,每天二十四(24)小时和每周七(7)天,以确保按照协议进行项目运行。
(b)
The Company shall also use its reasonable efforts to employ other
local labor in both skilled and unskilled capacities. The Company
shall develop and maintain training programs to train its personnel
in functional skills pertaining to operations and maintenance of
the Project to the standard of Prudent Utility Practices. The
Company’s training program shall be opened to at least four (4) EDC
employees per year.
公司也应尽最大努力雇佣有技能的和无技能的当地劳动力,制定培训计划使人员满足谨慎实用惯例标准里的项目运行维护技能要求。
公司每年至少应向4名EDC员工开放培训计划。
5.8
OPERATING COMMITTEE 运行委员会
Within sixty (60) days prior to the date
of Provisional Operation of the First Unit, the Parties shall
establish an Operating Committee in accordance with Schedule 7. The
obligations and responsibilities of the Operating Committee and the
rules governing meetings of the Operating Committee shall be as set
out in Schedule 7.
在第一台机组临时运行日前的60天内,双方应按照附录7成立运行委员会。运行委员会的义务和责任以及管理运行委员会会议的规则将在附录7里陈述。
5.9
RECORDS 记录
Each Party shall keep complete and
accurate records and all other data required by each of them for
the purposes of proper administration of this Agreement including
an accurate and up-to-date operating log at the Project with
records of:
各方应保持完整和准确的记录,及为执行本协议所需的其他数据,包括准确的和及时更新的运行日志,其记录着:
(a)
real and Reactive Power production for each Hour and bus voltages
at all times;
每小时有功和无功功率产生的电力及每个时刻的母线电压;
(b)
changes in operating status, 运行状态的变化
(c)
Planned Outages, Short Term Maintenance Outages and Forced Outages
(including partial derations); 计划停机,短期维护停机和强制停机(包括部分减额)
(d)
heat rates, ramp up and ramp down rates, the times required for
Cold, Warm and Hot Start ups; and 热耗,产能提升和下降率,冷启动,暖启动和热启动的次数要求
(e)
any unusual conditions found during inspections.
在巡检中发现的任何异常情况。
All such records shall be maintained
pursuant to Prudent Utility Practices for a minimum of sixty (60)
months after the creation of such records or data and for any
additional length of time required by regulatory agencies with
jurisdiction over the Parties, provided however that the Parties
shall not dispose of or destroy any such records after such sixty
(60) month period without giving at least thirty (30) days prior
written notice to the other Party and the notified Party shall have
the right to require such records in lieu of such disposal or
destruction upon giving at least ten (10) days prior written notice
to the other Party. Either Party shall have the right, upon
reasonable prior notice to the other Party, to examine and copy the
records and data of the other Party relating to the construction,
operation and maintenance of the Project at any time during normal
office hours during the period such records and data are required
to be maintained.
所有的记录应在此类数据或记录创立后,根据审慎实用惯例保存60个月,或双方管理机构要求的更长时间。在 60个月的期限后,如果未提前30天以书面形式通知另一方,另一方不得处理或销毁这些纪录,且被通知方可提起那10通知另一方要求获得这些记录。任何一方均有权,在事先通知另一方时,在需要保持这些记录和数据期间中的正常办公时间里,可随时检查和复制另一方关于施工、运行及维护该项目的记录和数据。
5.10 Fuel Supply 燃料供给
(a)
The Company shall procure and purchase all Fuel (including all
related transportation and insurance services)
required for the operation of the Project and the generation of
electric energy in accordance herewith and will maintain no less
than a thirty (30) day stock of primary Fuel at the
Project. The Company shall use its reasonable
efforts at all times during the Term to acquire Coal from at least
one internationally-recognized coal supplier with the capability to
deliver the related Coal requirements of the PROJECT (each, a
“Qualified Fuel Supplier”) and one or more Fuel Transporters to
transport fuel from the source to the Site in each case on
commercially competitive terms, consistent with market conditions
and the Fuel mixture needs of the PROJECT under one or more firm
procurement contracts (each, a “Long-Term Fuel
Contract”).
公司应根据本协议采购所有项目运行和发电所需的燃料(包括相关运输和保险业务),并且保证项目有不少于30天的主要燃料储存。公司应在合同期内尽力从国际认可的煤炭供应商获得项目用煤(各称为“合格的燃料供应商”)及与一个或多个将燃料从来源运至现场的运输人合作,获得商业竞争条款下、符合市场条件和项目燃料多种需求的一个或多个采购合同(各称为“长期燃料合同”)。
(b)
If at any time during the Term the full amount of Fuel requirements
are not provided for under one or more Long-Term Fuel Contracts, or
any existing Fuel Supplier or Fuel Transporter is in default of its
obligations under the terms of its agreement with the Company to
supply and/or transport Fuel to the PROJECT, the Company may submit
to Qualified Fuel Suppliers and/or Fuel Transporters an RFP for one
or more Long-Term Fuel Contracts in accordance with this Section
5.10. At least one year before the scheduled expiration of any
Long-Term Fuel Contract, the Company shall issue an RFP to provide
the Fuel and/or transportation services covered by such expiring
Long-Term Fuel Contract. At least sixty (60) days prior to
submitting to Qualified Fuel Suppliers an RFP for any Long-Term
Fuel Contract, the Company will provide a copy of such RFP to EDC
together with a list of the Qualified Fuel Suppliers to whom the
RFP will be sent. The Company shall include in any RFP issued under
this Section 5.10 at least five Qualified Fuel Suppliers designated
by the Company (if available). Any RFP shall also be conducted in
accordance with Section 4.3.
如果在合同期间,一个或多个长期燃料合同项下未提供燃料总量要求,或任一现有燃料供应商或运输人未履行与公司签订的项目燃料供应和/或运输协议项下的义务,则公司根据本5.1条可能向合格的供应商或运输人提供一份RFP以签订一份或多份长期燃料合同。在任何长期燃料合同计划到期前至少1年,公司应发布一份RFP来提供该到期合同所覆盖的采购和/或运输服务。在向合格燃料供应商提供签署长期燃料合同的RFP前至少60天,公司应向EDC提供该RFP副本并随附合格燃料供应商的名单。公司在本条5.10下发布的任何RFP应包含至少5名合格燃料供应商(如有)。任一RFP应同样遵从第4.3条。
Prior to the date of Provisional Operation of the First Unit, the
Parties shall mutually agree upon Fuel sampling and testing
procedures, such as the Short Proximate Analysis Test, to be used
to determine compliance with this Agreement and the Fuel Supply
Agreements, and acceptable testing procedures are set forth in
Schedule 17 of this Agreement. The Parties agree that EDC shall
have the right to approve the selection of any testing laboratory
for testing Fuel deliveries for use in the PROJECT and that the
Company will provide samples of Fuel shipments to EDC upon
reasonable request. Within fifteen (15) days after the end of each
Billing Period, the Company shall give EDC copies of all invoices
for Fuel paid or incurred during such Billing Period.
第一台机组临时运行日之前,双方需一致同意燃料取样和试验程序,例如用于确定符合本协议和燃料采购协议的工业分析试验,同时合理的测试程序于本协议附录17中陈述。合同各方同意EDC有权批准选择测试实验室用于测试项目中使用的燃料。在各结算期结束后15日内,公司应向EDC提供该结算期内所有燃料采购的发票复印件。
(c)
The Company shall have the right at any time to obtain Fuel and/or
transportation services pursuant to a Spot Market Fuel Contract
without prior EDC review or approval if (i) the Total Fuel Cost
pursuant to such Spot Market Fuel Contract (determined over the
term of the Sport Market Fuel Contract) is no greater than the
Total Fuel Cost pursuant to the Long-Term Fuel Contracts to which
the Company is a party (determined for the 90-day period ending on
the date such Spot Market Fuel Contract commences) or (ii) Fuel
deliveries to the PROJECT pursuant to any Long-Term Fuel Contract
to which the Company is party have been interrupted or suspended
for force majeure or other reasons not due to the fault or
negligence of the Company, provided that the Company shall only be
entitled to pass-through to, and recover from EDC the delivered
cost of Fuel used by the Company for purchases under (c)(i)and
(c)(ii) above in an amount up to but no greater than the Total Fuel
Cost that the Company would have incurred under the Long-Term Fuel
Cost that was interrupted or suspended (for the same amount of Fuel
that is purchased under such Spot Market Fuel Contract), until, in
the case of any Spot Market Fuel Contract under (c)(ii) such time
as EDC has approved the terms and pricing of any such Spot Market
Fuel Contract(s), and provided further that the foregoing
limitation on recovery of the costs of purchases under any Spot
Market Fuel Contract shall not apply if the Company was required to
make such purchases due to EDC’s withholding of consent to the
execution, termination, modification, amendment or waiver of the
provisions of any Long-Term Fuel Contract. The Company shall
provide EDC with a summary of the material terms and conditions of
each Spot Market Fuel Contract within thirty (30) days following
its purchase of fuel or transportation services pursuant to such
contract.
公司有权在没有EDC预先审核批准时根据现货市场燃料合同采购燃料和/或运输服务的条件为(i)现货市场燃料合同的燃料总成本(期间至现货市场燃料合同结束)不高于公司为合同方的长期燃料合同的燃料总成本(期间为现货燃料合同签订后90天),或(ii)公司作为合同方的长期燃料合同项下的项目燃料交付量因不可抗力或其他非公司过错或疏忽的原因被中止或暂停,但公司仅有权从EDC获得(c)(i)和(c)(ii)项下已用燃料成本,总价将不大于公司因中断或暂停而产生的长期燃料成本,直至EDC批准了(c)(ii)项下任何现货市场合同的条款和定价。上述现货市场燃料合同项下成本的补偿限制不适用于公司因 EDC不同意执行、终止、修改或放弃任一长期燃料合同的条款而需要的采购。公司应在其购买燃料或运输服务的30天内,向EDC提供现货市场合同主要条款和条件的摘要。
(d)
If the Company desires to select the bid of a Fuel Supplier and/or
Fuel Trnsporter that is not ranked as a Most Favorable Bid
following a related RFP, it may do so. If (i) the Company selects a
bid that is not a Most Favorable Bid following an RFP for Fuel
and/or transportation services or (ii) unreasonably terminates any
Long-Term Fuel Contract, then, in either such case, in determining
the AFPn in Schedule 14, the Fuel costs for pass-through related to
the Fuel supply and/or transportation services affected by such
selection or such unreasonable termination shall be equal to the
costs that would have been incurred under a Long-Term Fuel Contract
made pursuant to a Most Favorable Bid or the Long-Term Fuel
Contract so terminated, adjusted for calorific value differences
between the Fuel used and the Fuel that would have been used under
an implicated agreement, if any, until the occurrence of the next
RFP.
如公司希望选择一个燃料供应商和/或燃料运输商的报价,而其并非相关RFP中排名的最佳报价,(i)公司选择一个非最优报价的报价提供燃料和/或运输服务,或者(ii)无理由地终止任一长期燃料合同,则在任一情况下,在确认附录14中的AFPn时,由该选择或该无理由终止产生的燃料采购和/或运输成本应等于根据最优报价或终止的长期燃料合同项下的成本,根据使用的燃料和相关协议下应使用的燃料间的热值差调整,直到下一个RFP出现。
5.11 CESSATION OF OPERATION OR
ABANDONMENT BY THE COMPANY
运行中止或公司放弃
(a)
NOTWITHSTANDING any other provision of this Agreement, and SUBJECT
to any prior right of the Lenders under the Direct Agreement or any
other agreement entered into by the Company and EDC with the
Lenders or any of them, if the Company shall have ceased to operate
the Project after the Commercial Operation Date for at least
seventy-two (72) consecutive hours following a Company Event of
Default and the expiration of the relevant cure period under
Section 15 (or, if applicable, any longer period granted by EDC to
the Lenders under the Direct Agreement or any other agreement
entered by the Company and EDC with the Lenders or any of them)
then, EDC shall immediately be entitled to enter the Site and
operate the Project per Prudent Utility Practices until
either:
尽管在本协议中有其他的规定并遵守直接协议中或由公司和EDC与贷款人签订的其他协议中的贷款人的优先权,在商业运行日后,如果发生第15条项下的公司违约事件并且补救期(如适用,在直接协议或由公司和EDC与贷款人签订的其他协议项下EDC授予贷款人较长期限)已满,公司停止运行项目连续超过七十二(72)小时,届时EDC有权立即进入现场并运行项目,直到:
(i)
EDC exercises its right to terminate this Agreement under Section
15.4; or
EDC行使其在第15.4 条项下的权利,终止本协议;或
(ii)
the Company or any Nominated Company demonstrates to the reasonable
satisfaction of EDC that it has the capability to and shall resume
normal operations of the Project.
公司或其他指定公司向EDC提供EDC合理满意的证明,证明其有能力并将恢复项目的正常运行。
(b)
Payment during Suspension of Operation. The
Company shall permit EDC to operate the Project pursuant to Section
5.11(a) provided that EDC shall be responsible for any and all
operation and maintenance costs (including scheduled maintenance)
of the Project, and the Company shall be paid only that element of
Electricity Payments which is calculated to cover the payment of
interest and installment of principal and the funding of all
reserve accounts as required by the Lenders and all other financing
costs charged by the Lenders in accordance with debt repayment
schedule in the applicable Financing Agreements for the financing
of the Project.
运行暂停期间的付款:公司应允许EDC依据第5.10(a)条运行项目,条件是EDC应负责所有项目运行维护的费用(包括定期维护),并仅向公司支付电费的下列部分:贷款当期的本金、利息和贷款人要求的储备账户资金,以及贷款人根据适用的融资协议下的债务偿还计划收取的其他融资费用。
5.12 FAILURE OF THE EDC
SYSTEM EDC系统故障
The calculation of Electricity Payments
under Schedule 14 shall not be affected by or include any
deductions by reason of: (a) any failure, restriction or outage of
transmission facilities on the EDC side of the Metering Point; and
(b) any action which the Company, in accordance with the EDC Grid
Code, is obliged or entitled to take due to any frequency excursion
on the EDC System which triggers a protective device under the
Specifications.
计算附录14项下的电费支付应不受下列原因的影响或扣减,由于:(a)在计量点EDC一侧输电设施的故障、限制或中断;
及(b)由于EDC系统的频率偏移触发保护装置,公司依据EDC电网规范有义务或有权采取的任何行动。
6.
INTERCONNECTION
互联
6.1
INTERCONNECTION FACILITIES 互联设施
6.1.1
The Company shall be responsible for designing, constructing,
installing and testing the Interconnection Facilities in accordance
with the Technical Specifications set out in Schedule 4, such that
they are capable of connecting to the Interconnection
Point.
公司应负责依照附录4 中规定的技术规范,设计、施工、安装并试验互联设施,使其能够与联锁点连接。
6.1.2
The Interconnection Point shall be at the 230 kV/22kV terminal
substation at Preah Sihanouk Province as as defined in Schedule 4
and which will be located on the Substation Site. The Preah
Sihanouk Province Terminal Substation shall be completed and owned
by EDC.
互联点应位于附录4定义的位于西哈努克省变电站现场的230kV/22kV终端变电站。西哈努克省终端变电站由EDC完成并拥有。
6.1.3
EDC and the Company shall cooperate in completing the
Interconnection of the Interconnection Facilities to the
Interconnection Point for the purpose of permitting the supply of
Electricity to and from the Project.
EDC和公司应合作完成互联设施和互联点的联接,以允许向项目供电并从项目输出电力。
6.1.4
The Parties shall cooperate to test the Interconnection Facilities
in order for the interconnection to the EDC System on or before the
Scheduled Energization Date and prior to the start-up and
commissioning of the Plant. The Company shall give to EDC a sixty
(60) days’ advance notice of such testing.
双方应合作进行互联设施试验,以便在计划通电日及电厂启动和调试前与EDC系统联接。公司应在试验前60天通知EDC。
6.2
PROTECTIVE DEVICES 防护装置
(a)
The Company shall provide protective devices as part of the
Interconnection Facilities in accordance with the EDC
specifications set out in Schedule 4. Any modifications, changes or
upgrading of the Interconnection Facilities that becomes necessary
due to subsequent changes to EDC’s System, EDC’s Technical
Requirements / Cambodian Grid Code, after the Commercial Operation
Date, may be carried out by the Company, and EDC shall reimburse
the Company for the costs thereof. Any modifications, changes or
upgrades to the related EDC System necessary due to subsequent
changes to the Project (other than changes required by a
Change-in-Law or the EDC Grid Code), after the Commercial Operation
Date, may be carried out by EDC, and the Company shall reimburse
EDC for such costs.
公司应按照在附录4 中规定的EDC规范,提供保护装置,该防护装置为互联设施的一部分。在商业运行日期后,由于EDC系统、EDC技术要求以及柬埔寨电网规范的更改,公司应对互联设施进行必要的更改或升级,EDC应向公司偿还相关费用。在商业运行日期后,由于项目的更改(非法律变更或EDC电网规范要求的更改),由于项目的更改EDC应对EDC系统进行必要的更改或升级,公司应向EDC偿还相关费用。
(b)
EDC and the Company shall notify the other Party as soon as
possible of any changes to either the Project or the EDC System
where such changes may affect the proper coordination of protective
devices between the two systems.
EDC或公司应尽快的通知另一方,关于项目或EDC系统的任何改变,如果这种变化可能影响两个系统之间保护装置的妥善协调。
6.3
TESTING OF INTERCONNECTION FACILITIES AND EDC
SYSTEM互联设施和EDC系统的试验
EDC and the Company shall cooperate in
testing the Interconnection Facilities and the EDC System prior to
the Commercial Operation Date and at such other times thereafter as
EDC may reasonably require. All such testing shall be carried out
in a timely manner and in accordance with Paragraph 4 of Schedule
5.
EDC及公司应在商业运行日期之前和在EDC合理要求的其他时间合作进行互联设施和EDC系统的试验。所有此类试验应按照附录5的第4段的规定及时进行。
6.4
ENERGIZATION OF THE INTERCONNECTION FACILITIES AND
SWITCHYARD
互联设施和开关站通电
EDC and the Company shall energize the
Inerconnection Facilities and the PROJECT’s switchyard on a date
(the “Energization Date”) occurring no more than five (5) Days
after the Company successfully completes the testing of the
Interconnection Facilities and PROJECT Switchyard in accordance
with Paragraph 4 of Schedule 5.
在公司根据附录5第4段成功完成互联设施和项目开关站试验后5天内,EDC和公司应将互联设施和项目开关站通电,该通电日期即“通电日”。
6.5
ENERGIZATION OF A UNIT 机组通电
Prior to synchronization of a Unit with
the EDC System, the Company shall provide to EDC a certificate
confirming that the Unit has successfully completed the final
synchronization tests set forth in Schedule 5.
在机组与EDC系统同步前,公司应向EDC提供证明,确认机组已成功完成附录5中规定的最终同步试验。
6.6
OPERATION OF EDC
SYSTEM
EDC系统的运行
EDC shall own and operate the EDC
System. The Company shall observe and monitor the operation and
performance of the EDC System as to the extent it relates to the
Company’s operational performance of the Project, and shall as so
required by EDC, advise EDC on the performance of the EDC
System.
EDC应拥有和运行EDC系统。公司应观察和监测EDC系统的运行和性能,如果它关系到公司的项目运行。公司应根据EDC的要求对EDC系统的运行提出建议。
7.
METERING SYSTEM 计量系统
7.1
METERS 表计
The Company shall own, install and
maintain, at the Company’s expense, the Metering System and the
Backup Metering Equipment as described in Schedule 6.
公司应按照附录6中的规定,拥有、安装并维护计量系统和备用计量设备,费用由公司承担。
7.2
INSTALLATION OF METERS 表计的安装
The Company shall install the Metering
System at the location as agreed between EDC and the Company in
accordance with Schedule 6.
公司应当根据附录6的规定,在EDC和公司同意的位置安装计量系统。
7.3
TESTING AND RE-CALIBRATION OF METERS
表计的试验和重新校准
The Company shall be responsible for
inspecting and testing the Metering System for accuracy by a
mutually acceptable independent qualified testing authority at its
own expense in accordance with Schedule 6.
公司应当按照附录6的规定,通过双方认可并且具有独立资格的实验室,对计量系统的精确性进行检查和测试,费用由公司承担。
7.4
READING OF ENERGY METERS电表读表
The Company will carry out readings on a
daily basis. The procedure for reading the meters
shall be in accordance with Schedule 6. 公司应按照附录6规定的读表程序每日读表。
7.5
METER ACCURACY 表计的精确度
The total metering system accuracy shall
be 0.2% or better. Should total metering system accuracy be
measured above 0.2%, the Company will immediately report this to
EDC for their inspection, and arrange for meters to be tested for
accuracy and re-calibrated.
总计量系统的精确度应不超过0.2%,如果总计量系统精确度的测量高于0.2%,公司应立即报告EDC,并安排精确度检测和重新校验。
7.6
SEALING, REPAIR AND REPLACEMENT OF METERS表计的封铅、修理和更换
7.6.1
Requirements on Sealing of Meters. The Metering
System and the Backup Metering System shall comply with the
requirements set out in Schedule 6 and shall be jointly sealed by
both Parties. The seals shall be broken only by personnel from the
Company in the presence of EDC personnel when the Metering System
or the Backup Metering System is to be inspected, tested, or
adjusted.
表计封铅的要求。主要计量系统和备用计量系统应当符合附录6中规定的要求,并且应当由双方共同进行封铅。如果需要对计量系统和备用计量系统技能型检查、测试和调校时,应当有EDC的人员在场的情况下,方可由公司的人员对封铅进行拆除。
7.6.2
Repair, Recalibration or Replacement of Meters.
When any component of the Metering System is found to be outside
acceptable limits of accuracy, the Company shall, at its cost,
repair, recalibrate or replace such component of the Metering
System. Similarly, when any component of the Back-up Metering
System is found to be outside acceptable limits of accuracy, the
Company shall, at its cost, forthwith repair, recalibrate or
replace such component of the Backup Metering System.
表计的修理、重新校准或更换。如果发现计量系统的任何组件的精确性超出可接受范围,公司应当对计量系统中的此类组件,自费进行修理、重新校准或予以更换。同样,如果发现备用计量系统的任何组件的精确性超出可接受范围,公司应当对备用计量系统中的此类组件,自费进行修理、重新校准或予以更换。
8.
COMPENSATION, PAYMENT AND BILLING 赔偿、付款和结算
8.1
COMMERCIAL OPERATIONS PROGRAM 商业运行计划
(a)
Following the Commercial Operation Date and otherwise as provided
in this Section 8, the Company shall make available Net Dependable
Capacity at all times other than during downtime in accordance with
Section 2.5 and EDC shall purchase and accept capacity and
electricity (of at least the least the Minimum Take of Electricity)
(as set out in Schedule 13).
在商业运行日后并根据本第8条规定,公司应始终提供净可靠容量,除非根据第2.5条停机。EDC应购买和接受容量和电力(至少购买最低购电量)( 在附录13中规定)。
(b)
The Commercial Operation Date shall be a date agreed by EDC and the
Company occurring no more than five (5) Days after EDC has received
the certificate with respect to the Last Unit of each phase,
confirming that the last Unit of each phase, has successfully
completed the Commissioning Tests as required under Schedule 5
certifying the test results of such test. Prior
to the Commercial Operation Dates of each phase, and from time to
time during Provisional Operation, the Company shall issue to EDC
an availability notice based upon the results of the Capacity Test,
which shall also specify the Dependable Capacity of the Project
during the period of Provisional Operation and following completion
of Commissioning Tests of the Last Unit of each phase, as of the
Commercial Operation Date. 商业运行日期应由EDC
和公司协商确定,该日期应不晚于EDC收到本期最后一台机组的相关证明后的5天,该证明确认本期最后一台机组已成功完成附录5规定的调试试验并说明试验结果。在每期商业运行日期前以及临时运行期间,公司应基于容量试验结果向EDC发出可用性通知,说明项目在每期最后一台机组完成调试试验后的临时运行期间直到商业运行日期的可靠容量。
8.2
ELECTRICITY PAYMENTS 电费支付
The amount of payments for capacity and
energy delivered by the Project (collectively, the “Electricity
Payments”) shall be determined in accordance with the provisions of
Sections 8 and 12 and Schedules 13 and 14 principally and also with
the other provisions of this
Agreement.
对交付项目容量和电力支付的金额(统称“电费支付”)应根据第8条、第12条、附录13和14以及本协议的其他条款确定。
8.3
PAYMENT PRIOR TO THE COMMERCIAL OPERATION DATE OF EACH
PHASE
各期商业运行日前的支付
(a)
Prior to the date of Provisional Operation of a Unit of each phase
or the Commercial Operation Date of each phase, as the case may be,
if Section 8.3(b) does not apply, EDC shall pay to the Company, in
accordance with Section 8.6 and Section 8.7, for each kWh of
electrical output delivered from the relevant Stage to EDC during
the preceding month an amount equal to the Company’s actual Fuel
procurement and transportation, fuel oil, limestone and consumables
costs (including VAT on such purchases and other governmental
impositions charged on such purchases) incurred for generating such
output, provided that documentary evidence of such costs has been
provided by the Company to EDC. EDC shall not be
liable for any other costs incurred by the Company.
在各期机组临时运行日期或各期商业运行日期前,如果第8.3(b)条不适用,如果公司已向EDC提供书面证明,EDC应依据第8.6条和8.7条就上月向EDC交付的每千瓦小时电力输出向公司支付公司实际燃料采购运输成本、燃油、石灰石和消耗品费用(包括采购的增值税或其他政府征收费用)。EDC对公司产生的任何其他费用不承担责任。
(b)
Prior to the Commercial Operation Date of each phase, following
completion of the Commissioning Tests for a Unit as evidenced by a
certificate of the Independent Engineer confirming that the Unit
has successfully completed the Commissioning Tests as required
under Schedule 5 certifying the test results of such test, such
Unit shall enter into Provisional Operation as of and on the date
agreed by EDC and the Company occurring no more than five (5) Days
after EDC has received certificate with respect to that
Unit. For the Unit that is in Provisional
Operation, EDC shall pay to the Company for each month the
Electricity Payments for the Net Electrical Output and Payments for
Minimum Take in accordance with the provisions of Schedule 13 and
Schedule 14.
在各期商业运行日前,在完成机组的调试试验(机组成功完成附录5规定的调试试验并经独立工程师确认),机组应进入临时运行,临时运行日期应由EDC和公司协商确定,该日期应不晚于EDC收到相关证明后的5天。EDC每月应向公司支付净电输出的电费和最小购电量付款。
(c)
If the Commercial Operation Date of each phase, as the case may be,
does not occur by the Scheduled Commercial Operation Date of each
phase due to any combination of the factors set forth below, EDC
shall make payments based on the Minimum Take as calculated under
Section 2 of Schedule 13 converted to a daily rate at the Non-Fuel
Component of the tariff rate:
如果因下列综合原因导致各期商业运行日期未能在计划日期实现,EDC应基于最低购电量支付,最低购电量按照附录13第2条的公式转换成非燃料构成的每日费率计算:
(i)
the occurrence of any Force Majeure-Political; and/or
发生政治不可抗力,和/或
(ii)
any delay in energizing the Interconnection
Facilities and the PROJECT Switchyard that
prevents the export of power from the Project after the
Scheduled Energization Date, EDC’s inability to
provide back-feed power to the PROJECT to synchronize or to
dispatch a Unit so as to allow for timely completion of testing and
commissioning of that Unit.
延误互联设施和项目开关站的通电导致项目无法在计划通电日后输出电力,EDC无法向项目提供同步或调度机组所需倒送电以按时完成机组试验调试。
For purposes of determining the amount
due under this Section 8.3(c), the Minimum Take kWh shall be
multiplied by the number of Units affected by any such condition
and divided by the total units of each phase, as the case may
be.
在确定第8.3(c)条项下的应付金额时,最低购电量kWh应乘以受该情况影响的机组数并除以各期的总机组数,视情况而定。
During any period that EDC is obligated
to make payments to the Company under this Section 8.3(c), the
Scheduled Commercial Operation Date of each phase, as the case may
be, shall be extended by the same period that the underlying cause
and its consequences remain in effect and the Company’s performance
of its related obligations shall be excused for the same
period.
在EDC有义务根据第8.3(c)向公司付款的期限内,各期的计划商业运行日期应延长,延长期限等于公司受影响无法履行义务的期限。