简明合同格式 (FIDIC绿皮书 英文版)

标签:
fidic合同杂谈 |
分类: 工程招投标设计施工监理技术 |

FIDIC Short Form of Contract
简明合同格式 (FIDIC绿皮书 英文版)
CONTENTS
Agreement 4
Offer
Acceptance
Appendix
General Conditions
1
1.1
The Contract
Persons
Dates, Times and Periods
Money and Payments
Other Definitions
1.2
1.3
1.4
1.5
1.6
2
2.1
2.2
2.3
2.4
3
3.1
3.2
4
4.1
4.2
4.3
4.4
5
5.1
5.2
6
6.1
7
7.1
7.2
7.3
7.4
8
8.1
8.2
9
9.1
9.2
10
10.1
10.2
10.3
10.4
10.5
11
12
13
Default by Contractor
14
14
14.1
14.2
14.3
15
.15.1
15.2
15.3
INDEX
Particular Conditions
Rules for
Adjudication
Notes for
Guidance
Notes
Agreement
The Employer is _____________of
The Contractor is ____________of
The Employer desires the execution of certain Works known as
OFFER
The Contractor has examined the documents listed in the Appendix which forms part of this Agreement and offers to execute the Works in conformity with the Contract for the sum of _____________________(in words)_________________(in figures) (________________________)
or such other sum as may be ascertained under the Contract.This offer, of which the Contractor has submitted two signed originals, may be accepted by the Employer by signing and returning one original of this document to the Contractor before________________________(date)
The Contractor understands that the Employer is not bound to accept the lowest or any offer received for the Works.
Signature: ________________ Date: _______________
Name: _______________ Authorised to sign on behalf of (organization
Capacity: __________________
ACCEPTANCE
The Employer has by signing below, accepted the Contractor’s offer and agree that in consideration for the execution of the Contract. This Agreement comes into effect on the date when the Contractor receives one original of this document signed by the Employer.
Signature: ___________________________ Date: __________________________
Name: ______________________________ Authorised to sign on behalf of (organization
Capacity:
___________________________
APPENDIX
This Appendix forms part of the Agreement.
[Note:
with the exception of the items for which the Employer’s
requirements have been inserted, the Contractor shall complete the
following information before submitting his offer.]
Item
General Conditions
General Provisions
1.1Definitions
In the Contract as defined below, the words and expressions defined shall have the following meanings assigned to them, except where the context requires otherwise:
1.1.1
1.1.2
1.1.3
Persons
1.1.4
1.1.5
1.1.6
Dates,Times and Periods
1.1.7
1.1.8
1.1.9
Money and
Payments
1.1.10
Other Definitions
1.1.12
1.1.13
1.1.14 “Force Majeure” means an exceptional event or circumstance: which is beyond a Party’s control; which such Party could not reasonably have provided against before entering into the Contract; which, having arisen, such Party could not reasonably have avoided or overcome; and, which is not substantially attributable to the other Party.
1.1.15
1.1.16
1.1.17
1.1.18
1.1.19
Interpretation
1.2
1.3
Priority of Documents
1.4 The law of the Contract is stated in the Appendix.
Communications
1.5 Wherever provisions is made for the giving or issue of any notice, instruction, or other communication by any person, unless otherwise specified such communication shall be written in the language stated in the Appendix and shall not be unreasonably withheld or delayed.
Statutory Obligations
The
Contractor shall comply with the laws of the countries where
activities are performed. The Contractor shall give all notices and
pay all fees and other charges in respect of Works.
The Employer
Provision of Site
2.1 The Employer shall provide the Site and right of access thereto at the times stated in the Appendix.
Permits and Licences
2.2 The Employer shall, if requested by the Contractor, assist him in applying for permits, licences or approvals which are required for the Works.
2.3 Employer’s Instructions
The
Contractoe shall comply with all instructions given by the Employer
in respect of the Works including the susn of all or part of
the Works.
2.4 Approvals
No approval or consent or absence of comment by the Employer or the Employer’s representative shall affect the Contractor’s obligations.
Employer’s Representatives
3.1Authorised Person
One of the Employer’s personnel shall have authority to act for him. This authorised person shall be as stated in the Appendix, or as otherwise notified by the Employer to the Contractor.
3.2Employer’s Representative
The Employer may also appoint a firm or individual to carry out certain duties. The appointee may be named in the Appendix, or notified by the Employer to the Contractor from time to time. The Employer shall notify the Contractor of the delegated duties and authority of this Employer’s representative.
The Contractor
4.1General Obligations
The Contractor shall carry out the Works properly and in accordance with the Contract. The Contractor shall provide all supervision, labour, Materials, Plant and Contractor’s Equipment which may be required. All Materials and Plant on Site shall be deemed to be the property of the Employer.
4.2Contractor’s
The
Contractor shall submit to the Employer for consent the name and
particulars of the person authorized to receive instructions on
behalf of the Contractor.
4.3Subcontracting
The Contractor shall not subcontract the whole of the Works. The Contractor shall not subcontract any part of the Works without the consent of the Employer.
4.4Performance Security
If stated in the Appendix, the Contractor shall deliver to the Employer within 14 days of the Commencement Date a performance security in a form and form a third party approved by the Employer.
Design by Contractor
5.1Contractor’s Design
The Contractor shall carry out design to the extent specified, as referred to in the Appendix. The Contractor shall promptly submit to the Employer all designs prepared by him. Within 14 days of receipt the Employer shall notify any comments or, if the design submitted is not in accordance with the Contract, shall reject it stating the reasons. The Contractor shall not contract any element of the permanent work designed by him within 14 days after the design has been submitted to the Employer or where the design for that element has been rejected. Design that has been rejected shall be promptly amended and resubmitted. The Contractor shall resubmit all designs commented on taking these comments into account as necessary.
5.2
Responsibility for The Contractor shall remain responsible for his
tendered Design
Employer’s Liabilities
6.1Employer’s Liabilities
In this Contract, Employer’s Liabilities mean:
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)
n)
o)
p)
Time for Completion
7.1
7.2
Within the time stated in the Appendix, the Contractor shall submit to the Employer a programme for the Works in the form stated in the Appendix.
7.3 Extension of Time
Subject to Sub-Clause 10.3, the Contractor shall be entitled to an extension to the Time for Completion if he is or will be delayed by any of the Employer’s Liabilities.
7.4 Late Completion
If the Contractor fails to complete the Works within the Time for Completion, the Contractor’s only liability to the Employer for such failure shall be to pay the amount stated in the Appendix for each day for which he fails to complete the Works.
Taking-Over
8.1 Completion
The Contractor may notify the Employer when he considers that the Works are complete.
8.2Taking-Over Notice
The Employer shall notify the Contractor when he considers that the Contractor has completed the Works stating the date accordingly. Alternatively, the Employer may notify the Contractor that the Works, although not fully complete, are ready for taking over, stating the date accordingly.
The Employer shall take over the Works upon the issue of this notice. The Contractor shall promptly complete any outstanding work and, subject to Clause 9, clear the Site.
Remedying Defects
9.1Remedying Defects
The Employer may at any time prior to the expiry of the period stated in the Appendix, notify the Contractor of any defects or outstanding work. The Contractor shall remedy at no cost to the Employer any defects due to the Contractor’s design, Materials, Plant or workmanship not being in accordance with the Contract.
The cost of remedying defects attributable to any other cause shall be valued as a Variation. Failure to remedy any defects or complete outstanding work within a reasonable time of the Employer’s notice shall entitle the Employer to carry out all necessary work at the Contractor’s cost.
9.2 Uncovering and Testing
The Employer may give instruction as to the uncovering and/or testing of any work. Unless as a result of any uncovering and/or testing it is established that the Contractor’s design, Materials, Plant or workmanship are not in accordance with the Contract, the Contractor shall be paid for such uncovering and/or testing as a Variation in accordance with Sub-Clause 10.2.
Variation and Claims
10.1 Right to Vary
The Employer may instruct Variations.
10.2 Valuation of Variations
Variations shall be valued as follows:
a)
b)
c)
d)
e)
10.3 Early Warning
The Contractor’s entitlement to extension to the Time for Completion or additional payment shall be limited to the time and payment which would have been due if had given prompt notice and had taken all reasonable steps.
10.4 Right to Claim
If the Contractor incurs Cost as a result of any of the Employer’s Liabilities, the Contractor shall be entitled to the amount of such Cost. If as a result of any of the Employer’s Liabilities, it is necessary to change the Works, this shall be dealt with as a Variation.
10.5 Variation and Claim
The
Contractor shall submit to the Employer anProcedure
Contract Price and Payment
11.1 Valuation of the Works
The Works shall be valued as provided for in the Appendix, subject to Clause 10.
11.2 Monthly Statements
The Contractor shall be entitled to be paid at monthly intervals:
a)
b)
The Contractor shall submit each month to the Employer a statement showing the amounts to which he considers himself entitled.
11.3 Interim Payments
Within 28 days of delivery of each statement, the Employer shall pay to the Contractor the amount shown in the Contractor’s statement less retention at the rate stated in the Appendix, and less any amount for which the Employer has specified his reasons for disagreement. The Employer shall not be bound by any sum previously considered by him to be due to the Contractor.
The Employer may withhold interim payments until he receives the performance security under Sub-Clause 4.4 (if any).
11.4 Payment of First
Half
of
11.5 Payment of Second Half
The remainder of the retention shall be paid by the Employer to the Contractor within 14 days after either the expiry of the period stated in the Appendix, or the remedying of notified defects or the completion of outstanding work, all as referred to in Sub-Clause 9.1, whichever is the later.
11.6 Final Payment
Within 42 days of the latest of the events listed in Sub-Clause 11.5 above, the Contractor shall submit a final account to the Employer together with any documentation reasonably required to enable the Employer to ascertain the final Contract Value.
11.7 Currency
Payment shall be in the currency stated in the Appendix.
11.8 Delayed Payment
The Contractor shall be entitled to interest at the ratestated in the Appendix for each day the Employer fails to pay beyond the prescribed payment period.
Default
12.1Default by Contractor
If the Contractor abandons the Works, refuses or fails tocomply with a valid instruction of the Employer or fails to proceed expeditiously and without delay, or is, despite a written complaint, in breach of the Contract, the Employer may give notice referring to this Sub-Clause and stating the default.
If the Contractor has not taken all practicable steps to remedy the default within 14 days after the Contractor’s receipt of the Employer’s notice, the Employer may by a second notice given within a further 21days, terminate the Contract. The Contractor shall then demobilise from the Site leaving behind Materials and Plant and any Contractor’s Equipment which the Employer instructs in the second notice is to be used until the completion of the Works.
12.2 Default by Employer
If the Employer fails to pay in accordance with the Contract, or is, despite a written complaint, in breach of the Contract, the Contractor may give notice referring to this Sub-Clause and stating the default. If the default is not remedied within 7 days after the Employer’s receipt of this notice, the Contractor may suspend the execution of all or parts of the works.
12.3 Insolvency
If a Party is declared insolvent under any applicable law, the other Party may be by notice terminate the Contract immediately. The Contractor shall then demobilize from the Site leaving behind, in the case of the Contractor’s insolvency, any Contractor’s Equipment which the Employer instructs in the notice is to be used until the completion of the Works.
12.4 Payment upon
After termination, the Contractor shall be entitled toTermination payment of the unpaid balance of the value of the Works executed and of the Materials and Plant reasonably delivered to the Site, adjusted by the following:
a)
b)
c)
d)
The net balance due shall be paid or repaid within 28 days of the notice of termination.
Risk and Responsibility
13.1 Contractor’s Care
The
Contractor shall take full responsibility for the care of
Works
Unless the loss or damage happens as a result of an Employer’s Liability, the Contractor shall indemnify the Employer, the Employer’s contractors, agents and employees against all loss or damage happening to the Works and against all claims or expense arising out of the Works caused by a breach of the Contract, by negligence or by other default of the Contractor, his agents or employees.
13.2 Force Majeure
If a Party is or will be prevented from performing any of its obligations by Force Majeure, the Party affected shall notify the other Party immediately. If necessary, the Contractor shall suspend the execution of the Works and, to the extent agreed with the Employer, demobilize the Contractor’s Equipment.
If the event continues for a period of 84 days, either Party may then give notice of termination which shall take effect 28 days after the giving of the notice.
After termination, the Contractor shall be entitled to payment of the unpaid balance of the value of the Works executed and of the Materials and Plant reasonably delivered to the Site, adjusted by the following:
a)
b)
c)
The net balance due shall be paid or repaid within 28 days of the notice of termination.
Insurance
14.1Extent of Cover
The Contractor shall, prior to commencing the Works, effect and thereafter maintain insurances in the joint names of the Parties:
a)
b)
c)
14.2 Arrangements
All insurances shall conform with any requirements detailed in the Appendix. The policies shall be issued by insurers and in terms approved by the Employer. The Contractor shall provide the Employer with evidence that any required policy is in force and that the premiums have been paid.
All payments received from insures relating to loss or damage to the Works shall be held jointly by the Parties and used for the repair of the loss or damage or as compensation for loss or damage that is not to be repaired.
14.3 Failure to insure
If the Contractor fails to effect or keep in force any of the insurances referred to in the previous Sub-Clauses, or fails to provide satisfactory evidence, policies or receipts, the Employer may, without prejudice to any other right or remedy, effect insurance for the cover relevant to such default and pay the premiums due and recover the same as a deduction from any other monies due to the Contractor.
Resolution of Disputes
15.1Adjudication
Unless settled amicably, any dispute or difference which arises between the Contractor and the Employer out of or in connection with the Contract, including any valuation or other decision of the Employer, shall be referred by either Party to adjudication in accordance with the attached Rules for Adjudication (“the Rules”). The adjudicator shall be any person agreed by the Parties. In the event of disagreement, the adjudicator shall be appointed in accordance with the Rules.
15.2 Notice of Dissatisfaction
If a Party is dissatisfied with the decision of the adjudicator or if no decision is given within time set out in the Rules, the Party may give notice of dissatisfaction referring to this Sub-Clause within 28 days of receipt of the decision or the expiry of the time for the decision. If no notice of dissatisfaction is given within specified time, the decision shall be final and binding on the Parties. If notice of dissatisfaction is given within the specified time, the decision shall be binding on the Parties who shall give effect to it without delay unless and until the decision of the adjudicator is revised by an arbitrator.
15.3 Arbitration
A dispute which has been the subject of a notice of dissatisfaction shall be finally settled by a single arbitrator under the rules specified in the Appendix. In the absence of agreement, the arbitrator shall be designated by the appointing authority specified in the Appendix. Any hearing shall be held at the place specified in the Appendix and in the language referred to in Sub-Clause 1.5.